Keep up to date on the status of the ATP. See below for the weekly construction schedule, including work scope and locations:

10/9/2017

Fall Restoration Update

Restoration of the Auburn Transmission Project (ATP) is largely complete. Throughout the remainder of the fall there will be limited activity related to silt fence removal, additional application of seed/fertilizer, additional grading, tree work, and other miscellaneous restoration items.

9/25/2017

Restoration Update

Restoration/project activities scheduled for this week include:

  • Mat removal and hauling in the Town of Throop in the vicinity of Turnpike Road; and
  • Restoration at various points throughout the project area, including in the City of Auburn in the vicinity of State Street Road, in the Town of Throop in the vicinity of Turnpike Road, Potter Road, Highbridge Road and Ball Road, in the Town of Brutus in the vicinity of Weedsport-Sennett and Shepherd Road, and in the Town of Elbridge in the vicinity of Hamilton Road and Kingston Road; and
  • Reseeding and fertilizing areas where vegetation has yet to achieve 80 percent growth, and removal of silt fence where vegetation has reached 80 percent growth.

9/18/2017

Restoration Update

Restoration/project activities scheduled for this week include:

  • Mat removal and hauling in the Towns of Brutus and Sennett in the vicinity of Weedsport-Sennett, and in the Town of Elbridge in the vicinity of Jordan Road, Halfway Road, State Route 5 and Kester Road; and
  • Roadway/work space restoration at various points throughout the project area, including in the Towns of Brutus and Sennett in the vicinity of Weedsport-Sennett, and in the Town of Elbridge in the vicinity of Jordan Road, Halfway Road, State Route 5 and Kester Road.

9/11/2017

Restoration Update

Restoration/project activities scheduled for this week include:

  • Mat removal and hauling in the Town of Brutus in the vicinity of Jericho Road, and in the Town of Elbridge in the vicinity of Kingston Road and Halfway Road; and
  • Roadway/work space restoration at various points throughout the project area, including in the Town of Throop in the vicinity of Potter Road, in Town of Brutus in the vicinity of Jericho Road and Shepherd Road, and in the Town of Elbridge in the vicinity of Kingston Road and Halfway Road.

9/5/2017

Restoration Update

Restoration/project activities scheduled for this week include:

  • Mat removal and hauling in the Town of Throop in the vicinity of Potter Road and Highbridge Road, in Town of Brutus in the vicinity of Jericho Road, and in the Town of Elbridge in the vicinity of Kingston Road; and
  • Roadway/work space restoration at various points throughout the project area, including in the Town of Throop in the vicinity of Potter Road and Highbridge Road, in Town of Brutus in the vicinity of Jericho Road, and in the Town of Elbridge in the vicinity of Kingston Road.

8/28/2017

Restoration Update

Restoration/project activities scheduled for this week include:

  • Mat removal and hauling in the Town of Throop in the vicinity of Potter Road and Reyer Road, and in Town of Brutus in the vicinity of Jericho Road, State Route 5 and Stevens Road; and
  • Roadway/work space restoration at various points throughout the project area, including in the Town of Throop in the vicinity of Potter Road and Reyer Road, and in the Town of Brutus in the vicinity of Jericho Road, State Route 5 and Stevens Road.

8/21/2017

Restoration Update

Restoration/project activities scheduled for this week include:

  • Mat removal and hauling in the Town of Throop in the vicinity of Potter Road and the cell tower access road, and in Town of Brutus in the vicinity of State Route 5 and Stevens Road;
  • Roadway/work space restoration at various points throughout the project area, including in the Town of Throop in the vicinity of Potter Road and Reyer Road, and in the Town of Brutus in the vicinity of State Route 5 and Stevens Road; and
  • Labeling/stenciling structure numbers in the National Grid right-of-way.

8/14/2017

Restoration Update

Restoration/project activities scheduled for this week include:

  • Mat removal and hauling in the Towns of Brutus and Sennett in the vicinity of State Route 34, and in Town of Elbridge in the vicinity of State Route 5 and Rolling Wheels Raceway;
  • Roadway/work space restoration at various points throughout the project area, including in the Town of Throop in the vicinity of Reyer Road, Potter Road and Manrow Road, in the Towns of Brutus and Sennett in the vicinity of State Route 34, and in the Town of Elbridge in the vicinity of State Route 5, Rolling Wheels Raceway and Millstone Golf Course; and
  • Labeling/stenciling structure numbers in the National Grid right-of-way.

8/7/2017

Restoration Update

Restoration/project activities scheduled for this week include:

  • Mat removal and hauling in the Town of Throop in the vicinity of Highbridge Road, and in the Towns of Brutus and Sennett in the vicinity of State Route 34 and Tanner Road, and in Town of Elbridge in the vicinity of State Route 5, Rolling Wheels Raceway and Millstone Golf Course;
  • Roadway/work space restoration at various points throughout the project area, including in the Town of Brutus in the vicinity of  Tanner Road, and in the Town of Elbridge in the vicinity of State Route 5, Rolling Wheels Raceway and Millstone Golf Course; and
  • Labeling/stenciling structure numbers in the National Grid right-of-way.

7/31/2017

Restoration Update

Restoration/project activities scheduled for this week include:

  • Mat removal and hauling in the Town of Throop in the vicinity of Turnpike Road and Potter Road, and in the Town of Brutus in the vicinity of Tanner Road;
  • Roadway/work space restoration at various points throughout the project area, including in the Towns of Brutus and Throop in the vicinity of Centerport Road, Ball Road and Tanner Road; and
  • Labeling/stenciling structure numbers in the National Grid right-of-way.

7/24/2017

Restoration Update

Restoration/project activities scheduled for this week include:

  • Mat removal and hauling in the Town of Throop in the vicinity of Turnpike Road and Potter Road;
  • Roadway/work space restoration at various points throughout the project area, including in the Towns of Brutus and Throop in the vicinity of Centerport Road, Ball Road and Tanner Road;
  • Traffic sign removal throughout the project area; and
  • Labeling/stenciling structure numbers in the National Grid right-of-way progressing west to east.

7/17/2017

Construction/Restoration Update

Updated 7/20/2017: NYSEG Line 972 was placed in service today.

Anticipated work scheduled for this week includes:

  • Work in the City of Auburn in the vicinity of State Street Substation and in the Town of Elbridge in the vicinity of Elbridge Substation related to the re-energization of Line 972 following the bussing of the two existing National Grid 115-kV lines in the west-east portion of the project route;
  • Mat removal and hauling in the City of Auburn and Town of Throop in the vicinity of State Street Road, Turnpike Road and Potter Road; and
  • Roadway restoration at various points throughout the project area, including in the Towns of Brutus and Throop in the vicinity of Ball Road.

7/11/2017

Project Update

The newly constructed 14.5 mile NYSEG Line 710 was energized early in the evening on July 11, 2017. This 115-kV transmission line runs north from State Street Substation in the City of Auburn through the Town of Throop, and then runs east to the Elbridge Substation through the Towns of Brutus, Sennett and Elbridge and the Village of Elbridge. 

We will continue to publish updates related to ongoing restoration work, as well as the busing of the existing National Grid 115-kV lines in that 10.3 mile portion of the project route.

7/10/2017

Construction Week 39

Anticipated work scheduled for this week includes:

  • Work in the City of Auburn in the vicinity of State Street Substation and in the Town of Elbridge in the vicinity of Elbridge Substation related to the upcoming energizing of the newly constructed NYSEG Line 710;
  • Mat removal and hauling in the City of Auburn and Town of Throop in the vicinity of State Street Road, Turnpike Road, Reyer Road and Highbridge Road;
  • Roadway restoration at various points throughout the project area, including in the Towns of Brutus and Sennett in the vicinity of Tanner Road, Weedsport Sennett Road and Shepherd Road, and in the Town of Elbridge from Hamilton Road west; and
  • Wire work throughout the west-east portion of the project route related to the busing of the two existing National Grid 115-kV lines in that corridor.

7/5/2017

Construction Week 38

Anticipated work scheduled for this week includes:

  • Work in the City of Auburn in the vicinity of State Street Substation and in the Town of Elbridge in the vicinity of Elbridge Substation related to the upcoming energizing of the newly constructed NYSEG Line 710;
  • Mat removal at various points throughout the project area, including in the Town of Throop along Potter Road, and in the Towns of Brutus and Sennett in the vicinity of Weedsport Sennett Road, Shepherd Road and Jericho Road;
  • Roadway restoration at various points throughout the project area, including in the Town of Brutus in the vicinity of Tanner Road; and
  • Environmental work, including maintenance of erosion controls, as necessary, throughout the project area.

6/26/2017

Construction Week 37

Anticipated work scheduled for this week includes:

  • Wire work in the City of Auburn in the vicinity of State Street Substation and in the Town of Elbridge in the vicinity of Elbridge Substation;
  • Mat removal and roadway restoration at various points throughout the project area, including in the Towns of Brutus and Sennett in the vicinity Shepherd Road and Jericho Road, and in the Town of Elbridge east of Kingston Road and in the vicinity Hamilton Road; and
  • Environmental work, including maintenance of erosion controls, as necessary, throughout the project area.

6/19/2017

Construction Week 36

Please note that while normal construction hours are Monday through Saturday between 7:00 am and 7:00 pm, this week crews will be working late hours in the vicinity of Ball Road in the Towns of Brutus and Throop. This work will continue through Saturday and Sunday, June 24 and 25.

Anticipated work scheduled for this week includes:

  • Structure and wire work in the Towns of Brutus and Throop in the vicinity of Ball Road;
  • Mat removal and clean-up in the Towns of Brutus and Sennett in the vicinity of Shepherd Road, and in the Town of Elbridge in the vicinity of Jordan Road and Rolling Wheels Raceway;
  • Roadway restoration at various points throughout the project area, including in the Towns of Brutus and Sennett in the vicinity Shepherd Road, and in the Town of Elbridge east of Kingston Road and in the vicinity of Rolling Wheels Raceway; and
  • Environmental work, including maintenance of erosion controls, as necessary, throughout the project area.

6/12/2017

Construction Week 35

Anticipated work scheduled for this week includes:

  • Wire work in the Towns of Brutus, Sennett and Throop in the vicinity of Ball Road, State Route 34, Weedsport Sennett Road and Shepherd Road;
  • Mat removal and clean-up, and roadway restoration at various points throughout the project area, including in the Town of Brutus in the vicinity of Jericho Road, Stevens Road and State Route 5 and the Town of Elbridge in the vicinity of Jordan Road, Kingston Road and Halfway Road; and
  • Environmental work, including maintenance of erosion controls, as necessary, throughout the project area.

Please note that construction activities are authorized on a Monday through Saturday schedule between the hours of 7:00 am and 7:00 pm.

6/5/2017

Construction Week 34

Updated: Work is no longer scheduled for Sunday, June 11, 2017.  Normal construction hours are on a Monday through Saturday schedule between the hours of 7:00 am and 7:00 pm.

Anticipated work scheduled for this week includes:

  • Wire work in the Town of Throop in the vicinity of State Street Road, Turnpike Road, Potter Road, Reyer Road and Highbridge Road, and in the Towns of Brutus, Sennett and Throop in the vicinity of Ball Road, State Route 34, Weedsport Sennett Road and Shepherd Road;
  • Mat removal and restoration at various points throughout the project area, including mat removal in the Town of Elbridge in the vicinity of Kingston Road, Halfway Road and State Route 5; and
  • Environmental work, including restoration, and maintenance of erosion controls and roadways, as necessary, throughout the project area.

5/29/2017

Construction Week 33

Please note that while normal construction hours are on a Monday through Saturday schedule between the hours of 7:00 am and 7:00 pm, work is expected to take place this upcoming Sunday, June 4, 2017.

Anticipated work scheduled for this week includes:

  • Structure work, including spotting, framing and erection, in limited areas within the Town of Throop in the vicinity of Potter Road;
  • Wire work in the Town of Throop in the vicinity of State Street Road, Turnpike Road, Potter Road, Reyer Road and Highbridge Road, and in the Towns of Brutus, Sennett and Throop in the vicinity of Weedsport Sennett Road, Shepherd Road, Jericho Road, Stephens Road, State Route 5 and Ball Road;
  • Mat removal and restoration at various points throughout the project area, including mat removal in the Town of Elbridge in the vicinity of State Route 5; and
  • Environmental work, including installation of erosion controls, and road maintenance, as necessary throughout the project area.

5/22/2017

Construction Week 32

Anticipated work scheduled for this week includes:

  • Structure work, including spotting, framing and erection, in limited areas within the Town of Throop in the vicinity of Potter Road;
  • Wire work in the Town of Throop in the vicinity of State Street Road, Turnpike Road, Potter Road, Reyer Road and Highbridge Road, and in the Towns of Brutus and Elbridge in the vicinity of Weedsport Sennett Road, Shepherd Road, Jericho Road, Stephens Road and State Route 5;
  • Mat removal and restoration at various points throughout the project area, including mat removal in the Town of Elbridge in the vicinity of Kester Road; and
  • Environmental work, including installation of erosion controls, and road maintenance, as necessary throughout the project area.

Please note that while normal construction hours are on a Monday through Saturday schedule between the hours of 7:00 am and 7:00 pm, it is anticipated that wire work will last until 8:00 pm throughout the week between Weedsport Sennett Road in the Town of Brutus and Rolling Wheels Raceway in the Town of Elbridge.

No work is expected to take place on Memorial Day, May 29, 2017.

5/15/2017

Construction Week 31

Anticipated work scheduled for this week includes:

  • Foundation work in the Town of Throop in the vicinity of Potter Road, Reyer Road and Highbridge Road;
  • Structure work, including spotting, framing and erection, in the Town of Throop in the vicinity of State Street Road, Turnpike Road, Potter Road, Reyer Road, Highbridge Road and Centerport Road;
  • Wire work in the Town of Throop in the vicinity of State Street Road, Turnpike Road, Potter Road, Reyer Road and Highbridge Road, and in the Town of Elbridge in the vicinity of State Route 5, Hamilton Road, Jordan Road, Gorham Road and Kingston Road;
  • Mat removal and restoration at various points throughout the project area, including mat removal in the Town of Elbridge in the vicinity of Kester Road; and
  • Environmental work, including installation of erosion controls, and road maintenance, as necessary throughout the project area.

Please note that construction activities are authorized on a Monday through Saturday schedule between the hours of 7:00 am and 7:00 pm.

5/8/2017

Construction Week 30

Anticipated work scheduled for this week includes:

  • Foundation work in the Town of Throop in the vicinity of Turnpike Road, Potter Road, Highbridge Road and Centerport Road;
  • Structure work, including spotting, framing and erection, in the Town of Throop in the vicinity of State Street Road, Turnpike Road, Potter Road, Reyer Road, Highbridge Road and Centerport Road;
  • Wire work in the Town of Throop in the vicinity of Turnpike Road, Potter Road, Reyer Road, Highbridge Road and Centerport Road, and in the Town of Elbridge in the vicinity of State Route 5, Hamilton Road, Jordan Road, Gorham Road and Kingston Road; and
  • Environmental work, including installation of erosion controls, and road maintenance, as necessary throughout the project area.

Please note that construction activities are authorized on a Monday through Saturday schedule between the hours of 7:00 am and 7:00 pm.

5/1/2017

Construction Week 29

Anticipated work scheduled for this week includes:

  • Foundation work in the Town of Throop in the vicinity of State Street Road, Turnpike Road and Potter Road;
  • Structure work, including spotting, framing and erection, in the Town of Throop in the vicinity of State Street Road, Turnpike Road, Potter Road, Reyer Road, Highbridge Road and Centerport Road;
  • Wire work, including pulling conductor and dead-ending and clipping in wire, in the Town of Elbridge in the vicinity of Hamilton Road, Jordan Road, Gorham Road, Kingston Road, Halfway Road, State Route 5 and Kester Road;
  • Continuation of log removal and stump grinding throughout the project area, including work in the Town of Throop in the vicinity of Reyer Road, in the Town of Brutus and Sennett in the vicinity of Tanner Road, and in the Town of Elbridge in the vicinity of Millstone Golf Course; and
  • Environmental work, including installation of erosion controls, and road maintenance, as necessary throughout the project area.

Please note that construction activities are authorized on a Monday through Saturday schedule between the hours of 7:00 am and 7:00 pm

4/28/2017

Construction Week 28

Anticipated work scheduled for this week includes:

  • Foundation work in the Town of Throop in the vicinity of Ball Road;
  • Structure work, including spotting, framing and erection, in the Towns of Brutus and Sennett in the vicinity Weedsport Sennett Road;
  • Wire work, including pulling conductor and dead-ending and clipping in wire, in the Town of Throop in the vicinity of Highbridge Road, Centerport Road and Ball Road, and in the Town of Elbridge in the vicinity of Halfway Road, State Route 5 and Kester Road;
  • Continuation of log removal and stump grinding throughout the project area; and
  • Environmental work, including installation of erosion controls, and road maintenance, as necessary throughout the project area.

Please note that construction activities are authorized on a Monday through Saturday schedule between the hours of 7:00 am and 7:00 pm

4/17/2017

Construction Week 27

Anticipated work scheduled for this week includes:

  • Foundation work in the Town of Throop in the vicinity of Ball Road;
  • Structure work, including spotting, framing and erection, in the Towns of Brutus and Sennett in the vicinity Weedsport Sennett Road, and in the Town of Elbridge in the vicinity of State Route 5 and Kester Road;
  • Wire work, including pulling conductor and dead-ending and clipping in wire, from State Street Substation in the City of Auburn to Ball Road in the Town of Throop;
  • Road maintenance, as necessary, including matting in the Town of Brutus in the vicinity of Shepherd Road, Stevens Road and State Route 5, and gravel work in the Town of Elbridge in the vicinity of Rolling Wheels Raceway;
  • Continuation of log removal throughout the project area; and
  • Environmental work, including installation of erosion controls, as necessary throughout the project area.

Please note that construction activities are authorized on a Monday through Saturday schedule between the hours of 7:00 am and 7:00 pm

4/10/2017

Construction Week 26

Anticipated work scheduled for this week includes:

  • Survey work in the Town of Elbridge west of State Route 5 to stake structure locations;
  • Foundation work in the Town of Elbridge west of State Route 5;
  • Structure work, including spotting, framing and erection, in the Town of Throop in the vicinity of State Street Road, Turnpike Road, Potter Road, Reyer Road, Manrow Road, Highbridge Road and Centerport Road, in the Towns of Brutus and Sennett in the vicinity of State Route 34 and Tanner Road, and in the Town of Elbridge in the vicinity of Gorham Road;
  • Wire work, including pulling conductor and dead-ending and clipping in wire, from State Street Substation in the City of Auburn to Ball Road in the Town of Throop;
  • Logs will continue to be removed throughout the project area; and
  • Road maintenance and environmental work, including installation of erosion controls, as necessary throughout the project area.

Please note that construction activities are authorized on a Monday through Saturday schedule between the hours of 7:00 am and 7:00 pm

4/3/2017

Construction Week 25

Anticipated work scheduled for this week includes:

  • Installation of matting in theTown of Throop in the vicinity of Reyer Road, Potter Road, Manrow Road, Highbridge Road and Centerport Road;
  • Foundation work in the Town Sennett in the vicinity of Shepherd Road; and
  • Structure work, including spotting, framing and erection, in the Town of Throop in the vicinity of State Street Road, Turnpike Road, Potter Road, Reyer Road, Manrow Road, Highbridge Road and Centerport Road, in the Towns of Brutus and Sennett in the vicinity of State Route 34 and Tanner Road, and in the Town of Elbridge in the vicinity of Gorham Road, Kingston Road, Halfway Road, State Route 5 and Kester Road;
  • Wire work, including pulling conductor and preparation for wire pulling, from State Street Substation in the City of Auburn to Ball Road in the Town of Throop;
  • Logs will continue to be removed throughout the project area; and
  • Environmental work, including installation of erosion controls, as necessary throughout the project area.

Please note that construction activities are authorized on a Monday through Saturday schedule between the hours of 7:00 am and 7:00 pm

3/27/2017

Construction Week 24

Anticipated work scheduled for this week includes:

  • Installation of matting in theTown of Throop in the vicinity of Reyer Road, Potter Road, Manrow Road, Highbridge Road and Centerport Road;
  • Foundation work in the Town Sennett in the vicinity of Shepherd Road, and in the Town of Elbridge in the vicinity of Kingston Road, Halfway Road and Kester Road; and
  • Structure work, including spotting, framing and erection, in the Town of Throop in the vicinity of Turnpike Road, Potter Road, Reyer Road, Manrow Road, Highbridge Road and Centerport Road, in the Towns of Brutus and Sennett in the vicinity of State Route 34 and Tanner Road, and in the Town of Elbridge in the vicinity of Gorham Road, Kingston Road, Halfway Road, State Route 5 and Kester Road;
  • Wire work, including preparation for wire pulling, from State Street Substation in the City of Auburn to Turnpike Road in the Town of Throop;
  • Logs will continue to be removed throughout the project area; and
  • Environmental work, including installation of erosion controls, as necessary throughout the project area.

Please note that construction activities are authorized on a Monday through Saturday schedule between the hours of 7:00 am and 7:00 pm

3/20/2017

Construction Week 23

Anticipated work scheduled for this week includes:

  • Snow removal/sanding, as needed, at various points throughout the project area;
  • Installation of matting in theTown of Throop in the vicinity of State Street Road and Potter Road,;
  • Foundation work in the Town Sennett in the vicinity of Shepherd Road, and in the Town of Elbridge in the vicinity of Kingston Road, Halfway Road and Kester Road; and
  • Structure work, including spotting, framing and erection, in the Town of Throop in the vicinity of Turnpike Road and Highbridge Road, in the Towns of Brutus and Sennett in the vicinity of State Route 34 and Shepherd Road, and in the Town of Elbridge in the vicinity of Jordan Road; and
  • Log removal in the Town of Elbridge in the vicinity of in the vicinity of Halfway Road; and
  • Environmental work, including installation of erosion controls, as necessary throughout the project area.

Please note that construction activities are authorized on a Monday through Saturday schedule between the hours of 7:00 am and 7:00 pm

3/13/2017

Construction Week 22

Please note that due to the inclement weather, this week's work schedule is subject to change.

Anticipated work scheduled for this week includes:

  • Snow removal/sanding, as needed, at various points throughout the project area;
  • Installation of matting in the City of Auburn and Town of Throop in the vicinity of State Street Road, in the Towns of Brutus and Sennett in the vicinity of Weedsport Sennett Road, and in the Town of Elbridge in the vicinity of Kingston Road. Gravel road work is expected to take place in the Town of Brutus in the vicinity of Shepherd Road;
  • Foundation work in the Towns of Brutus and Sennett in the vicinity of Weedsport Sennett Road, and in the Town of Elbridge in the vicinity of Jordan Road, Gorham Road, Halfway Road and Kester Road; and
  • Structure work, including spotting, framing and erection, weather permitting; and
  • Chipping and chip removal in the Town of Elbridge in the vicinity of Halfway Road heading west. Log removal will continue at various points throughout the project area, weather permitting; and
  • Environmental work, including installation of erosion controls, as necessary throughout the project area.

Please note that construction activities are authorized on a Monday through Saturday schedule between the hours of 7:00 am and 7:00 pm

3/6/2017

Construction Week 21

Anticipated work scheduled for this week includes:

  • Installation of matting in the City of Auburn and Town of Throop in the vicinity of State Street Road, in the Town of Elbridge in the vicinity of Kingston Road;
  • Foundation work in the Town of Throop in the vicinity of Ball Road, in the Towns of Brutus and Sennett in the vicinity of Weedsport Sennett Road, Shepherd Road, Stevens Road and State Route 5, and in the Town of Elbridge in the vicinity of Jordan Road, Gorham Road, Kingston Road, Halfway Road and Kester Road; and
  • Structure work, including spotting, framing and erection, in the Town of Throop in the vicinity of Potter Road and Highbridge Road, in the Towns of Brutus and Sennett in the vicinity of State Route 34, Jericho Road and Stevens Road, and in the Town of Elbridge in the vicinity of Kester Road; and
  • Log removal, installation of erosion controls and snow removal/sanding, as needed, at various points throughout the project area.

Please note that construction activities are authorized on a Monday through Saturday schedule between the hours of 7:00 am and 7:00 pm

2/27/2017

Construction Week 20

Anticipated work scheduled for this week includes:

  • Installation of matting in the Towns of Brutus and Elbridge in the vicinity of State Route 5 and Hamilton Road;
  • Foundation work in the Town of Throop in the vicinity of Ball Road, in the Towns of Brutus and Sennett in the vicinity of Weedsport Sennett Road, Shepherd Road, Stevens Road and State Route 5, and in the Town of Elbridge in the vicinity of Kingston Road, Halfway Road and Kester Road; and
  • Structure work, including spotting, framing and erection, in the Town of Throop in the vicinity of Turnpike Road, Potter Road and Highbridge Road, and in the Town of Elbridge in the vicinity of Kingston Road and Halfway Road; and
  • Log removal, installation of erosion controls and snow removal/sanding, as needed, at various points throughout the project area.

Please note that construction activities are authorized on a Monday through Saturday schedule between the hours of 7:00 am and 7:00 pm.

2/20/2017

Construction Week 19

Anticipated work scheduled for this week includes:

  • Tree and brush clearing, removal and chipping in the Town of Elbridge in the vicinity of Jordan Road, Kingston Road and Halfway Road;
  • Installation of matting in the Town of Elbridge in the vicinity of Halfway Road, State Route 5 and Kester Road;
  • Foundation work in the City of Auburn in the vicinity of State Street Road, in the Town of Throop in the vicinity of Turnpike Road, Potter Road and Highbridge Road, and in the Town of Brutus in the vicinity Jericho Road; and
  • Structure work, including spotting, framing and erection, in the Town of Brutus in the vicinity of Shepherd Road, and in the Town of Elbridge in the vicinity of Kingston Road.

Please note that construction activities are authorized on a Monday through Saturday schedule between the hours of 7:00 am and 7:00 pm.

2/13/2017

Construction Week 18

Anticipated work scheduled for this week includes:

  • Tree and brush clearing, removal and chipping in the Town of Brutus in the vicinity of Shepherd Road, and in Town of Elbridge in the vicinity of Jordan Road, Kingston Road and Halfway Road;
  • Installation of matting in the Town of Elbridge in the vicinity of Halfway Road, State Route 5 and Kester Road;
  • Foundation work in the Towns of Brutus and Sennett in the vicinity of State Route 34 and Jericho Road, and in the Town of Elbridge in the vicinity of Hamilton Road; and
  • Structure work, including spotting, framing and erection, in the Towns of Brutus and Sennett in the vicinity of State Route 34, Tanner Road and Weedsport Sennett Road, and in the Town of Elbridge in the vicinity of Hamilton Road.

Please note that construction activities are authorized on a Monday through Saturday schedule between the hours of 7:00 am and 7:00 pm.

2/6/2017

Construction Week 17

Anticipated work scheduled for this week includes:

  • Tree and brush clearing, removal and chipping in the Town of Throop in the vicinity of Reyer Road, Potter Road and Highbridge Road, in the Town of Brutus in the vicinity of Shepherd Road, and in Town of Elbridge in the vicinity of Kingston Road and Halfway Road;
  • Gravel access road development in the in the Towns of Brutus and Sennett in the vicinity of Weedsport Sennett Road, and in the Town of Elbridge in the vicinity of Gorham Road and Kingston Road;
  • Installation of matting in the Town of Brutus in the vicinity of Weedsport Sennett Road, Shepherd Road and Jericho Road, and in the Town of Elbridge in the vicinity of Kingston Road;
  • Foundation work in the Town of Brutus in the vicinity of State Route 34, Tanner Road and Shepherd Road, and in the Town of Elbridge in the vicinity of  Hamilton Road; and
  • Structure work, including spotting, framing and erection, in the City of Auburn and Town of Throop in the vicinity of State Street Road, Turnpike Road and Potter Road, and in the Towns of Brutus and Sennett in the vicinity of State Route 34, Tanner Road and Weedsport Sennett Road.

Please note that construction activities are authorized on a Monday through Saturday schedule between the hours of 7:00 am and 7:00 pm.

1/30/2017

Construction Week 16

Anticipated work scheduled for this week includes:

  • Tree and brush clearing, removal and chipping in the Town of Elbridge in the vicinity of Hamilton Road, Halfway Road and Kester Road;
  • Gravel access road development in the Towns of Brutus and Throop in the vicinity of Ball Road, in the Towns of Brutus and Sennett in the vicinity of Weedsport Sennett Road, and in the Town of Elbridge in the vicinity of Gorham Road;
  • Installation of matting in the Town of Brutus in the vicinity of Shepherd Road, Jericho Road, State Route 5 and Stevens Road, and in the Town of Elbridge in the vicinity of Kingston Road;
  • Foundation work in the Town of Brutus in the vicinity of State Route 34, and in the Town of Elbridge in the vicinity of State Route 5, Rolling Wheels Raceway and Hamilton Road;
  • Structure work, including spotting, framing and erection, in the Town of Elbridge in the vicinity of State Route 5 and Rolling Wheels Raceway; and
  • Continued survey of right-of-way, access roads and structure locations in the Town of Elbridge, and in areas where necessary to support road building, drilling and structure crews.

Please note that construction activities are authorized on a Monday through Saturday schedule between the hours of 7:00 am and 7:00 pm.

1/23/2017

Construction Week 15

Anticipated work scheduled for this week includes:

  • Tree and brush clearing, removal and chipping in the Town of Sennett in the vicinity of Weedsport Sennett Road, and in the Town of Elbridge in the vicinity of Hamilton Road and Kingston Road;
  • Gravel access road development in the Towns of Brutus and Throop in the vicinity of State Route 34, Weedsport Sennett Road and Shepherd Road, and in the Town of Elbridge in the vicinity of Kingston Road;
  • Installation of matting in the Town of Brutus in the vicinity of Jericho Road, and in the Town of Elbridge in the vicinity of Jordan Road and Gorham Road;
  • Installation of stabilized construction entrances and erosion controls in the Towns of Brutus and Throop in the vicinity of State Route 34, Weedsport Sennett Road and Shepherd Road, and in the Town of Elbridge in the vicinity of Kingston Road;
  • Foundation work in the Town of Throop in the vicinity of Highbridge Road, and in the Town of Elbridge in the vicinity of State Route 5 and Hamilton Road;
  • Structure work, including spotting and setting bases, in the City of Auburn and Town of Throop in the vicinity of State Street Road and Turnpike Road; and
  • Continued survey of right-of-way, access roads and structure locations in the Town of Elbridge, and in areas where necessary to support road building, drilling and structure crews.

Please note that construction activities are authorized on a Monday through Saturday schedule between the hours of 7:00 am and 7:00 pm.

1/16/2017

Construction Week 14

Anticipated work scheduled for this week includes:

  • Tree and brush clearing, removal and chipping in the Town of Elbridge in the vicinity of State Route 5, Rolling Wheels Raceway, Hamilton Road, Gorham Road and Kingston Road;
  • Gravel access road development in the Towns of Throop and Brutus in the vicinity of Ball Road, and in the Town of Elbridge in the vicinity of State Route 5, Rolling Wheels Raceway, Hamilton Road and Gorham Road;
  • Installation of matting in the Town of Elbridge in the vicinity of State Route 5 and Rolling Wheels Raceway;
  • Installation of stabilized construction entrances and erosion controls in the Towns of Throop and Brutus in the vicinity of Ball Road;
  • Foundation drilling and pouring of concrete in the Town of Throop north of Turnpike Road in the vicinity of Reyer Road, Potter Road and Highbridge Road;
  • Structure work, including spotting and setting bases, in the City of Auburn and Town of Throop in the vicinity of State Street Road and Turnpike Road (south of Turnpike); and
  • Continued survey of right-of-way, access roads and structure locations in areas where necessary to support road building and drilling crews. It is expected that survey activities will take this place in the Town of Elbridge east of Kingston Road.

Please note that construction activities are authorized on a Monday through Saturday schedule between the hours of 7:00 am and 7:00 pm.

1/9/2017

Construction Week 13

Anticipated work scheduled for this week includes:

  • Tree and brush clearing, removal and chipping in the Town of Elbridge in the vicinity of State Route 5, Rolling Wheels Raceway and Hamilton Road;
  • Gravel access road development in the Towns of Throop and Brutus in the vicinity of Ball Road, in the Towns of Brutus and Sennett in the vicinity of State Route 34 and Tanner Road, in the Town of Brutus in the vicinity of Shepherd Road, and in the Town of Elbridge in the vicinity of Hamilton Road and Gorham Road;
  • Installation of matting in the Town of Throop in the vicinity of Potter Road and Highbridge Road, in the Towns of Throop and Brutus in the vicinity of State Route 34, and in the Town of Elbridge in the vicinity of Hamilton Road;
  • Installation of stabilized construction entrances and erosion controls in the Town of Brutus in the vicinity of Tanner Road, and in the Town of Elbridge in the vicinity of Hamilton Road;
  • Foundation drilling and pouring of concrete in the Town of Throop north of Turnpike Road in the vicinity of Reyer Road, Potter Road and Highbridge Road; and
  • Continued survey of right-of-way, access roads and structure locations in areas where necessary to support road building and drilling crews. It is expected that survey activities will take this place in the Town of Elbridge east of Kingston Road.

Please note that construction activities are authorized on a Monday through Saturday schedule between the hours of 7:00 am and 7:00 pm.

1/3/2017

Construction Week 12

Anticipated work scheduled for this week includes:

  • Tree and brush clearing, removal and chipping in the Town of Brutus in the vicinity of Shepherd Road and Jericho Road, and in the Town of Elbridge in the vicinity of State Route 5, Rolling Wheels Raceway and Hamilton Road;
  • Gravel access road development in the Towns of Throop and Brutus in the vicinity of Ball Road, in the Towns of Brutus and Sennett in the vicinity of Tanner Road, and in the Town of Elbridge in the vicinity of Hamilton Road and Gorham Road;
  • Installation of matting in the Town of Throop in the vicinity of Reyer Road, Potter Road and Highbridge Road, in the Towns of Throop and Brutus in the vicinity of Ball Road, in the Towns of Brutus and Sennett in the vicinity of Tanner Road, and in the Town of Elbridge in the vicinity of Hamilton Road;
  • Installation of stabilized construction entrances and erosion controls in the Town of Brutus in the vicinity of Tanner Road, and in the Town of Elbridge in the vicinity of Hamilton Road;
  • Foundation drilling and pouring of concrete in the City of Auburn and Town of Throop between State Street Road and Turnpike Road, and in the Town of Throop in the vicinity of Reyer Road, Potter Road and Highbridge Road; and
  • Continued survey of right-of-way, access roads and structure locations. Survey activities will include areas not surveyed in previous weeks, and where necessary to support road building and drilling crews.

Please note that construction activities are authorized on a Monday through Saturday schedule between the hours of 7:00 am and 7:00 pm.

12/27/2016

Construction Week 11

Anticipated work scheduled for this week includes:

  • Tree and brush clearing, removal and chipping in the Towns of Brutus and Sennett in the vicinity Weedsport Sennett Road and Shepherd Road, and in the Town of Elbridge in the vicinity of State Route 5 east of Stevens Road;
  • Gravel access road development in the Towns of Throop and Brutus in the vicinity of Ball Road, in the Towns of Brutus and Sennett in the vicinity of Tanner Road, and in the Town of Elbridge in the vicinity of Hamilton Road and Gorham Road;
  • Installation of matting in the Town of Throop south of Turnpike Road, and in the vicinity of Manrow Road, Potter Road and Highbridge Road;
  • Installation of stabilized construction entrances and erosion controls in the Town of Brutus in the vicinity of Tanner Road, and in the Town of Elbridge in the vicinity of Hamilton Road;
  • Foundation drilling and pouring of concrete in the City of Auburn and Town of Throop between State Street Road and Turnpike Road, and in the Town of Throop in the vicinity of Potter Road and Highbridge Road; and
  • Continued survey of right-of-way, access roads and structure locations. Survey activities will include areas not surveyed in previous weeks, and where necessary to support road building and drilling crews.

Please note that construction activities are authorized on a Monday through Saturday schedule between the hours of 7:00 am and 7:00 pm. No work is scheduled for Saturday, December 31, 2016 or Monday, January 2, 2017.

12/19/2016

Construction Week 10

Anticipated work scheduled for this week includes:

  • Tree and brush clearing, removal and chipping in the Towns of Brutus and Sennett in the vicinity of State Route 34, Tanner Road, Weedsport Sennett Road, and Shepherd Road;
  • Gravel access road development in the Town of Brutus in the vicinity of Tanner Road, and in the Town of Elbridge in the vicinity of Hamilton Road and Gorham Road;
  • Installation of matting in the Town of Throop south of Turnpike Road, and in the vicinity of Manrow Road, Potter Road and Highbridge Road;
  • Installation of stabilized construction entrances and erosion controls in the Town of Brutus in the vicinity of Tanner Road, and in the Town of Elbridge in the vicinity of Hamilton Road;
  • Foundation drilling and pouring of concrete in the City of Auburn and Town of Throop between State Street Road and Turnpike Road, and in the Town of Throop north of Turnpike Road in the vicinity of Potter Road; and
  • Continued survey of right-of-way, access roads and structure locations. Survey activities will include areas not surveyed in previous weeks, and where necessary to support road building and drilling crews.

12/12/2016

Construction Week 9

Anticipated work scheduled for this week includes:

  • Tree and brush clearing, removal and chipping in the Town of Throop in the vicinity of Highbridge Road and Centerport Road;
  • Gravel access road development in the Town of Throop in the vicinity of Ball Road, in the Towns of Brutus and Sennett in the vicinity of State Route 34 and Tanner Road, and in the Town of Elbridge in the vicinity of Hamilton Road;
  • Installation of matting in the Town of Throop south of Turnpike Road, and in the vicinity of Manrow Road, Potter Road and Highbridge Road;
  • Installation of stabilized construction entrances and erosion controls in the Town of Throop in the vicinity of Highbridge Road, and in the Town of Brutus in the vicinity of Tanner Road;
  • Foundation drilling and pouring of concrete in the City of Auburn and Town of Throop south of Turnpike Road; and
  • Continued survey of right-of-way, access roads and structure locations. Survey activities will include areas not surveyed in previous weeks, and where necessary to support road building and drilling crews.

12/5/2016

Construction Week 8

Anticipated work scheduled for this week includes:

  • Tree and brush clearing, removal and chipping in the: City of Auburn and Town of Throop between State Street Road and Turnpike Road; Town of Throop in the vicinity of Highbridge Road; and Towns of Brutus and Throop between State Route 34 and Weedsport-Sennett Road;
  • Gravel access road development  in the Town of Throop in the vicinity of Centerport Road, in the Towns of Brutus and Sennett in the vicinity of State Route 34, and in the Town of Elbridge in the vicinity of Hamilton Road;
  • Installation of matting in the Town of Throop between Reyer Road and Potter Road;
  • Installation of stabilized construction entrances and erosion controls in the Town of Throop off of Potter Road at the existing cell tower access road, and in the Town of Brutus in the vicinity of Tanner Road;
  • Foundation drilling and pouring of concrete in the City of Auburn in the vicinity of the State Street Substation and Cold Spring Cemetery; and
  • Continued survey of right-of-way, access roads and structure locations. Survey activities will include areas not surveyed in previous weeks, and where necessary to support road building and drilling crews.

11/28/2016

Construction Week 7

Anticipated work scheduled for this week includes:

  • Tree and brush clearing/removal in the Town of Throop in the vicinity of Highbridge Road, Potter Road and Centerport Road;
  • Gravel access road development in the Town of Throop off of Potter Road at the existing cell tower access road, and in the Town of Brutus in the vicinity of Tanner Road;
  • Installation of matting in the Town of Throop off of Turnpike Road;
  • Installation of stabilized construction entrances and erosion controls at various points along the project right-of-way;
  • Continued survey of right-of-way, access roads and structure locations. Survey activities will include areas not surveyed in previous weeks due to unharvested crops, as well as survey of the existing right-of-way in the Town of Elbridge east of Kingston Road; and
  • Foundation drilling in the City of Auburn in the vicinity of the State Street Substation and Cold Spring Cemetery.

Please note that while construction activities are authorized on a Monday through Saturday schedule between the hours of 7:00 am and 7:00 pm, activities will continue to occur Monday through Friday between the hours of 7:00 am and 5:00 pm.

11/21/2016

Construction Week 6

Due to the inclement weather, construction activities will be limited this week. To the extent possible, this week's activities will be a continuation of last week's work. In addition, drilling crews will begin to mobilize in the vicinity of State Street Road in the City of Auburn and Town of Throop.

There is no work scheduled on the right-of-way on Thanksgiving Day or the day after.

11/14/2016

Construction Week 5

Anticipated work scheduled for this week includes:

  • Continued tree and brush clearing/removal in the vicinity of Cold Spring/State Street Cemetery in the City of Auburn. Tree cutting is expected to commence in the Town of Throop in the vicinity of Turnpike Road and Potter Road;
  • Continued access road development and matting along the NYSEG right-of-way in the Town of Throop in the vicinity of: Turnpike Road, Reyer Road, Potter Road, Highbridge Road and Centerport Road;
  • Development of access roads, and installation of stabilized construction entrances at points along the National Grid right-of-way in the Towns of Throop, Brutus and Sennett: in the vicinity of Ball Road, Weedsport Sennett Road and Shepherd Road;
  • Installation of erosion controls at various points along the project route as access road construction continues;
  • Continued survey of right-of-way, access roads and structure locations. Survey activities will continue along the NYSEG right-of-way in the Town of Throop, and along the National Grid right-of-way in the Towns of Throop, Brutus, Sennett and Elbridge with a focus on delineation of construction entrances and access roads.

It is expected that survey activities and mowing of the right-of-way will commence next week in the Town of Elbridge in the vicinity of Kingston Road, Halfway Road, State Route 5 and Kester Road.

11/7/2016

Construction Week 4

Anticipated work scheduled for this week includes:

  • Tree and brush clearing/removal in the vicinity of Cold Spring/State Street Cemetery in the City of Auburn;
  • Continued access road development and matting along the NYSEG right-of-way in the Town of Throop: off of Turnpike Road progressing south and Reyer Road progressing north, and in the vicinity of Highbridge and Centerport Roads;
  • Development of access roads, and installation of stabilized construction entrances at points along the National Grid right-of-way in the Towns of Throop, Brutus and Sennett: in the vicinity of Ball Road, Weedsport Sennett Road and Shepherd Road;
  • Installation of erosion controls at various points along the project route as access road construction commences; and
  • Continued survey of right-of-way, access roads and structure locations. Survey activities will continue in along the NYSEG right-of-way in the Town of Throop, and along the National Grid right-of-way in the Towns of Throop, Brutus and Sennett focused on delineation of construction entrances and access roads.

Please note that while construction activities are authorized on a Monday through Saturday schedule between the hours of 7:00 am and 7:00 pm, activities will occur Monday through Friday between the hours of 7:00 am and 5:00 pm in the near term.

10/31/2016

Construction Week 3

Anticipated work scheduled for this week includes:

  • Tree cutting in the vicinity of Cold Spring/State Street Cemetery in the City of Auburn;
  • Access road development and matting along the NYSEG right-of-way in the Town of Throop: off of Turnpike Road progressing south and Reyer Road progressing north, and in the vicinity of Highbridge and Centerport Roads;
  • Installation of erosion controls at various points along the project route as access road construction commences; and
  • Continued survey of right-of-way, access roads and structure locations. Survey activities will continue in along the NYSEG right-of-way in the Town of Throop, and along the National Grid right-of-way in the Towns of Throop, Brutus and Sennett focused on delineation of construction entrances and access roads.

10/24/2016

Construction Week 2

ATP construction crews will continue to mobilize and commence construction/site preparation activities. Anticipated work scheduled for this week includes:

  • Hand clearing in the vicinity of Cold Spring/State Street Cemetery in the City of Auburn;
  • Installation of erosion controls at various points along the project route as access road construction commences. Access road development and matting will commence along the NYSEG right-of-way in the City of Auburn and the Town of Throop. Activities will begin to occur in the vicinity of State Street, Turnpike Road, Potter Road, Reyer Road, High Bridge Road and Centerport Road;
  • Installation of traffic control signs at road crossings; and
  • Continued survey of right-of-way, access roads and structure locations. Survey activities will continue in along the NYSEG right-of-way in the Town of Throop, and an additional crew will commence activities along the National Grid right-of-way. Activities will start in the Town of Throop in the vicinity of Ball Road and continue east.

10/17/2016

Construction Week 1

ATP construction activities commenced on October 17, 2016. Work scheduled for this week includes:

  • Tree and brush clearing starting in the NYSEG right-of-way at the State Street Substation and continuing north at points where accessible;
  • Installation of traffic control signs at road crossings; and
  • Continued survey of right-of-way, access roads and structure locations. This week activity is planned for the NYSEG right-of-way north of Turnpike Road in the Town of Throop.

Pre-construction

Field crews are on the project right-of-way performing pre-construction activities including surveys, measurements, topographic and environmental evaluations. The work will be performed primarily on foot; however, ATVs and side-by-side utility vehicles (UTVs) may be used for transport purposes. Crews (forestry and survey) may remove vegetation using power equipment such as chainsaws or brush clearing devices in order to safely traverse the right-of-way, as well as place markings to delineate the right-of-way. All work will be performed during normal business hours and disturbance of land will be kept to a minimum.